Job Days Until Due Date Processing Time A 27 17 B 35 20 C 33

Job      Days Until Due Date       Processing Time

A                   27                                 17

B                   35                                 20

C                   33                                 30

D                   41                                 25

Given the following set of jobs waiting to run on a machine, Using the CR (critical ratio) how would you sequence these jobs?